USE WATCHBUILT AND MAKE GREAT THINGS HAPPEN




GENERAL HOSPITAL CENTER
Demolishing an old hospital building and constructing a new general hospital center within a specified timeframe and without mistakes demands a comprehensive and efficient approach. The WatchBuilt solution, with its emphasis on meticulous pre-planning, expert project management, collaborative design, and streamlined construction techniques, ensures the successful completion of such a project. By prioritizing quality, communication, and adaptability, a WatchBuilt solution paves the way for a state-of-the-art hospital center that meets the evolving healthcare needs of the community.
PROJECT TIMEFRAME
PROJECT INITIATION PHASE: 1 month
PRE-PLANNING PHASE: 2 months
DEMOLITION PHASE: 2 months
CONSTRUCTION PHASE: 12 months
INTERIOR AND SYSTEMS INSTALLATION PHASE: 4 months
FINISHING AND TESTING PHASE: 2 months
COMMISSIONING AND HANDOVER PHASE: 1 month
PROJECT CLOSURE PHASE: 1 month
TOTAL PROJECT DURATION: 25 months
​
Note: The timeframe provided is an example and can be adjusted based on the scale and complexity of the project. It is essential to develop a detailed project schedule with specific milestones and timelines during the planning phase to ensure a realistic timeframe for the demolition and construction of the new general hospital center. The WatchBuilt solution offers a 4D BIM-based automated and real-time solution to prevent construction project errors and overcome delays. This is case study is a demonstrative example.
​